Beach Nourishment

FEMA Public Notice - Notice of Availability of the Draft Statewide Programmatic Environmental Assessment (DSPEA)

SPEA Berm FPN

SPEA Berm Final

FEDERAL BEACH NOURISHMENT UPDATE :

USACE, N. Topsail Beach and Town Staff meet April 14th via WebEx to gain a status update on the federal storm mitigation project. USACE has had some shifts in the developed and un-developed properties, the net changes total three properties. Parking and Access standard submitted to USACE will be included int eh PPA.  USACE has been working with US Fish & Wildlife to widen the environmental windows. BOEM has requested a list of specific activities related to the BOEM leases. Once Fish and Wildlife receive public comment then BOEM can issue a permit for using sand sources outside of the 3-mile limit. Widening the environmental windows would allow contractors to dredge/place sand for a longer period of time, it will also cut down on timing and cost. Currently, regulations do not allow for dredging/sand placement from the middle of April to the middle of November of each calendar year. For Surf City, we are looking at an 18-month dredge timeframe with a 24-month contract. Surf City’s contract will overlap with NTB for an estimated one-year timeframe or total project timeframe of 36-months. Contract one will be for the Surf City portion of the project will begin at the Surf City Topsail Beach town line and run north estimating 6 million cubic yards of material. USACE’s data shows enough material to begin the Surf City portion of the project without the BOEM leases. After initial construction the contract will be amended to include areas to include BOEM leases available. The USACE expects to go out for bids in August with an expected bid opening date of September 17th. This would allow for a contract award in October 2021 with an expected start time of December 2021.  


The federal project is estimated to add an additional 12 million cubic yards of sand to the beach, build a new dune that is projected to be 25’ wide and 14’ high and widen the beach with a 6’ high and 300’ wide berm. Oceanfront citizens should have already turned in the perpetual easements. If you have not received your oceanfront easement please contact clerk@surfcitync.gov or 910-328-4131x106. This is NOT the same easement that was previously signed in 2019. This is a new easement required by USACE for the new beach nourishment project.

All Oceanfront Property Owners should have received a mailed notice regarding the request for an oceanfront easement for the USACE storm mitigation project. The project is slated to place sand on ALL oceanfront properties in Surf City. This is NOT the same easement that was previously signed in 2019. This is a new easement required by USACE for the new beach nourishment project. If you have questions regarding your easements please call 910-328-4131 x106 or email shobbs@townofsurfcity.com. This is a separate easement than those signed in 2019. ALL oceanfront property owners will need to sign the newly mailed easements and return them no later than July 10, 2020. We’ve received approximately 85% of all easements necessary for this project, so please make sure you get those in and thank you to those that have already!

USACE SC NTB Plans  

USACE SC NTB Plans II

Example Easement:

Dune Profile

OCEANFRONT PARCELS

Oceanfront owners can view their property by using the links below to view an Aerial Plat Map for each oceanfront parcel.
To find the map that corresponds with your property, please use the key below.


Aerial Plat Maps for Construction Easement Lines 
Beach Nourishment - Key